Use the Column Toggle Report to let user quickly choose columns to display when screen size is limited.

Choose Column Toggle Report as Region type.

Examples

1. Standard

Display a report where end users can select the columns to display at runtime. End users can then change the columns based on the width and orientation of the screen they are using to display the report.

Task Name Start Date End Date Status Assigned To Cost Budget
Decommission servers 13-DEC-19 11-MAR-20 Pending Al Bines $0.00 $500.00
Measure effectiveness of improved QA 13-DEC-19 12-JAN-20 Pending Myra Sutcliff $0.00 $1,500.00
Response to Customer Feedback 13-DEC-19 05-APR-20 Pending Russ Saunders $0.00 $6,000.00
User acceptance testing 28-DEC-19 31-MAR-20 Pending Russ Saunders $0.00 $2,500.00
End-user Training 30-JAN-20 12-APR-20 Pending Myra Sutcliff $0.00 $2,500.00
Rollout sample applications 03-APR-20 14-APR-20 Pending Pam King $0.00 $500.00
Installation 15-DEC-19 14-JAN-20 Pending Mark Nile $0.00 $1,500.00
Notify users 16-JAN-20 19-JAN-20 Pending Mark Nile $0.00 $200.00
Plan production release schedule 02-NOV-19 02-NOV-19 Closed Pam King $100.00 $100.00
Complete questionnaire 29-OCT-19 12-NOV-18 On-Hold Irene Jones $1,200.00 $800.00
Select servers for Development, Test, Production 14-SEP-19 19-SEP-19 Closed James Cassidy $200.00 $600.00
HR Support Systems 12-SEP-19 22-JAN-20 Closed Al Bines $300.00 $500.00
HR software upgrades 12-SEP-19 08-JAN-20 On-Hold Pam King $8,000.00 $7,000.00
Arrange for vacation coverage 12-SEP-19 11-NOV-19 On-Hold Russ Sanders $9,500.00 $7,000.00
Complete plan 19-SEP-19 25-OCT-19 Closed Mark Nile $3,000.00 $1,500.00
Check software licenses 23-OCT-19 24-OCT-19 Closed Mark Nile $200.00 $200.00
Create training workspace 12-OCT-19 19-OCT-19 Closed James Cassidy $500.00 $700.00
Publish links to self-study courses 12-OCT-19 12-OCT-19 Closed John Watson $100.00 $100.00
Identify point solutions required 14-OCT-19 16-OCT-19 Closed John Watson $200.00 $300.00
Install in development 18-OCT-19 18-OCT-19 Closed John Watson $100.00 $100.00
Identify owners 30-SEP-19 03-OCT-19 Closed Hank Davis $250.00 $300.00
Initial Draft Review 04-OCT-19 04-OCT-19 Closed Hank Davis $100.00 $100.00
Monitor Review Comments 04-OCT-19 11-NOV-19 Closed Hank Davis $450.00 $500.00
Implement bug tracking software 26-SEP-19 26-SEP-19 Closed Myra Sutcliff $100.00 $100.00
Review automated testing tools 27-SEP-19 26-OCT-19 Closed Myra Sutcliff $2,750.00 $1,500.00
Identify pilot applications 21-SEP-19 26-SEP-19 Closed Mark Nile $300.00 $500.00
Migrate pilot applications to 01-OCT-19 06-OCT-19 Closed Mark Nile $500.00 $500.00
Customize Software Projects software 26-OCT-20 01-DEC-19 Open Tom Suess $600.00 $1,000.00
Post-migration review 12-OCT-19 12-OCT-19 Closed Mark Nile $100.00 $100.00
User acceptance testing 14-OCT-19 15-OCT-19 Closed Mark Nile $600.00 $200.00
Enter base data (Projects, Milestones, etc.) 21-OCT-19 22-OCT-19 Closed Tom Suess $200.00 $200.00
Load current tasks and enhancements 23-OCT-19 27-OCT-19 Closed Tom Suess $400.00 $500.00
Document quality assurance procedures 27-OCT-19 30-NOV-19 On-Hold Myra Sutcliff $3,500.00 $4,000.00
Conduct project kickoff meeting 16-OCT-19 16-OCT-19 Closed Pam King $100.00 $100.00
Determine host server 17-OCT-19 18-OCT-19 Closed Tiger Scott $200.00 $200.00
Check software licenses 18-OCT-19 18-OCT-19 Closed Tom Suess $100.00 $100.00
Identify pilot users 16-OCT-19 17-OCT-19 Closed Scott Spencer $200.00 $200.00
Software Deliverable 18-OCT-19 31-OCT-19 Closed Scott Spencer $400.00 $500.00
Early Adopter Release 01-NOV-19 01-NOV-19 Closed Pam King $100.00 $100.00
Determine midtier configuration(s) 13-SEP-19 13-SEP-19 Closed James Cassidy $100.00 $100.00
Manage Training Activities 09-OCT-19 15-DEC-19 On-Hold John Watson $1,000.00 $2,000.00
Review feedback 20-NOV-19 26-NOV-19 On-Hold Irene Jones $200.00 $400.00
Plan rollout schedule 27-NOV-19 05-DEC-19 On-Hold Irene Jones $0.00 $750.00
Plan rollout schedule 21-OCT-19 13-NOV-19 On-Hold Al Bines $300.00 $1,000.00
Develop web pages 21-NOV-19 27-DEC-19 On-Hold Tiger Scott $800.00 $2,000.00
Purchase additional software licenses, if needed 29-DEC-19 29-DEC-19 On-Hold Tom Suess $0.00 $100.00
Investigate new Virus Protection software 09-NOV-19 24-NOV-19 Open Pam King $1,700.00 $1,500.00
Get RFPs for new server 24-OCT-19 14-NOV-19 Open Mark Nile $2,000.00 $1,000.00
Collect mission-critical spreadsheets 26-OCT-19 27-DEC-19 Open Pam King $2,500.00 $4,000.00
Create applications from spreadsheets 26-OCT-19 10-APR-20 Open Pam King $6,000.00 $10,000.00
Lock spreadsheets 26-OCT-19 10-APR-20 Open Pam King $1,000.00 $800.00
Send links to previous spreadsheet owners 27-OCT-19 12-APR-20 Open Pam King $1,000.00 $1,500.00
Customize solutions 19-OCT-19 11-JAN-20 Open John Watson $1,500.00 $4,000.00
Train developers / users 21-NOV-19 04-FEB-20 Pending John Watson $0.00 $8,000.00
Implement in Production 07-NOV-19 14-MAR-20 Open John Watson $200.00 $1,500.00
Migrate applications 26-OCT-19 01-JAN-20 Open Mark Nile $1,000.00 $8,000.00
Plan migration schedule 02-NOV-19 13-JAN-20 Open Mark Nile $1,500.00 $6,000.00
Publish Feedback application 06-NOV-19 15-MAR-20 Open Pam King $300.00 $12,000.00
Train developers on tracking bugs 01-DEC-19 20-JAN-20 On-Hold Myra Sutcliff $0.00 $2,000.00
End-user Training 08-NOV-19 03-JAN-20 Open John Watson $0.00 $2,000.00
Identify server requirements 12-SEP-19 13-SEP-19 Closed John Watson $100.00 $200.00
Specify security authentication scheme(s) 14-SEP-19 16-SEP-19 Closed John Watson $200.00 $300.00
Create pilot workspace 21-SEP-19 21-SEP-19 Closed John Watson $100.00 $100.00
Configure Workspace provisioning 21-SEP-19 21-SEP-19 Closed John Watson $200.00 $100.00
Run installation 22-SEP-19 22-SEP-19 Closed James Cassidy $100.00 $100.00
Obtain equipment specifications 14-NOV-19 17-NOV-19 Pending James Cassidy $0.00 $500.00
Purchase backup server 23-NOV-19 19-DEC-19 Pending Mark Nile $0.00 $3,000.00
Identify integration points 19-NOV-19 09-DEC-19 Pending Mark Nile $0.00 $2,000.00
Decommission machines 19-NOV-19 19-NOV-19 Pending Scott Spencer $0.00 $100.00
Map data usage 01-DEC-19 13-JAN-20 Pending Mark Nile $0.00 $8,000.00
Purchase new machines 05-JAN-20 30-JAN-20 Pending John Watson $0.00 $2,500.00
Import data 06-JAN-20 02-FEB-20 Pending John Watson $0.00 $1,000.00
Convert processes 14-DEC-19 11-FEB-20 Pending Pam King $0.00 $3,000.00

2. No Stripes

Display a report where end users can select the columns to display at runtime. End users can then change the columns based on the width and orientation of the screen they are using to display the report.

Task Name Start Date End Date Status Assigned To Cost Budget
Decommission servers 13-DEC-19 11-MAR-20 Pending Al Bines $0.00 $500.00
Measure effectiveness of improved QA 13-DEC-19 12-JAN-20 Pending Myra Sutcliff $0.00 $1,500.00
Response to Customer Feedback 13-DEC-19 05-APR-20 Pending Russ Saunders $0.00 $6,000.00
User acceptance testing 28-DEC-19 31-MAR-20 Pending Russ Saunders $0.00 $2,500.00
End-user Training 30-JAN-20 12-APR-20 Pending Myra Sutcliff $0.00 $2,500.00
Rollout sample applications 03-APR-20 14-APR-20 Pending Pam King $0.00 $500.00
Installation 15-DEC-19 14-JAN-20 Pending Mark Nile $0.00 $1,500.00
Notify users 16-JAN-20 19-JAN-20 Pending Mark Nile $0.00 $200.00
Plan production release schedule 02-NOV-19 02-NOV-19 Closed Pam King $100.00 $100.00
Complete questionnaire 29-OCT-19 12-NOV-18 On-Hold Irene Jones $1,200.00 $800.00
Select servers for Development, Test, Production 14-SEP-19 19-SEP-19 Closed James Cassidy $200.00 $600.00
HR Support Systems 12-SEP-19 22-JAN-20 Closed Al Bines $300.00 $500.00
HR software upgrades 12-SEP-19 08-JAN-20 On-Hold Pam King $8,000.00 $7,000.00
Arrange for vacation coverage 12-SEP-19 11-NOV-19 On-Hold Russ Sanders $9,500.00 $7,000.00
Complete plan 19-SEP-19 25-OCT-19 Closed Mark Nile $3,000.00 $1,500.00
Check software licenses 23-OCT-19 24-OCT-19 Closed Mark Nile $200.00 $200.00
Create training workspace 12-OCT-19 19-OCT-19 Closed James Cassidy $500.00 $700.00
Publish links to self-study courses 12-OCT-19 12-OCT-19 Closed John Watson $100.00 $100.00
Identify point solutions required 14-OCT-19 16-OCT-19 Closed John Watson $200.00 $300.00
Install in development 18-OCT-19 18-OCT-19 Closed John Watson $100.00 $100.00
Identify owners 30-SEP-19 03-OCT-19 Closed Hank Davis $250.00 $300.00
Initial Draft Review 04-OCT-19 04-OCT-19 Closed Hank Davis $100.00 $100.00
Monitor Review Comments 04-OCT-19 11-NOV-19 Closed Hank Davis $450.00 $500.00
Implement bug tracking software 26-SEP-19 26-SEP-19 Closed Myra Sutcliff $100.00 $100.00
Review automated testing tools 27-SEP-19 26-OCT-19 Closed Myra Sutcliff $2,750.00 $1,500.00
Identify pilot applications 21-SEP-19 26-SEP-19 Closed Mark Nile $300.00 $500.00
Migrate pilot applications to 01-OCT-19 06-OCT-19 Closed Mark Nile $500.00 $500.00
Customize Software Projects software 26-OCT-20 01-DEC-19 Open Tom Suess $600.00 $1,000.00
Post-migration review 12-OCT-19 12-OCT-19 Closed Mark Nile $100.00 $100.00
User acceptance testing 14-OCT-19 15-OCT-19 Closed Mark Nile $600.00 $200.00
Enter base data (Projects, Milestones, etc.) 21-OCT-19 22-OCT-19 Closed Tom Suess $200.00 $200.00
Load current tasks and enhancements 23-OCT-19 27-OCT-19 Closed Tom Suess $400.00 $500.00
Document quality assurance procedures 27-OCT-19 30-NOV-19 On-Hold Myra Sutcliff $3,500.00 $4,000.00
Conduct project kickoff meeting 16-OCT-19 16-OCT-19 Closed Pam King $100.00 $100.00
Determine host server 17-OCT-19 18-OCT-19 Closed Tiger Scott $200.00 $200.00
Check software licenses 18-OCT-19 18-OCT-19 Closed Tom Suess $100.00 $100.00
Identify pilot users 16-OCT-19 17-OCT-19 Closed Scott Spencer $200.00 $200.00
Software Deliverable 18-OCT-19 31-OCT-19 Closed Scott Spencer $400.00 $500.00
Early Adopter Release 01-NOV-19 01-NOV-19 Closed Pam King $100.00 $100.00
Determine midtier configuration(s) 13-SEP-19 13-SEP-19 Closed James Cassidy $100.00 $100.00
Manage Training Activities 09-OCT-19 15-DEC-19 On-Hold John Watson $1,000.00 $2,000.00
Review feedback 20-NOV-19 26-NOV-19 On-Hold Irene Jones $200.00 $400.00
Plan rollout schedule 27-NOV-19 05-DEC-19 On-Hold Irene Jones $0.00 $750.00
Plan rollout schedule 21-OCT-19 13-NOV-19 On-Hold Al Bines $300.00 $1,000.00
Develop web pages 21-NOV-19 27-DEC-19 On-Hold Tiger Scott $800.00 $2,000.00
Purchase additional software licenses, if needed 29-DEC-19 29-DEC-19 On-Hold Tom Suess $0.00 $100.00
Investigate new Virus Protection software 09-NOV-19 24-NOV-19 Open Pam King $1,700.00 $1,500.00
Get RFPs for new server 24-OCT-19 14-NOV-19 Open Mark Nile $2,000.00 $1,000.00
Collect mission-critical spreadsheets 26-OCT-19 27-DEC-19 Open Pam King $2,500.00 $4,000.00
Create applications from spreadsheets 26-OCT-19 10-APR-20 Open Pam King $6,000.00 $10,000.00
Lock spreadsheets 26-OCT-19 10-APR-20 Open Pam King $1,000.00 $800.00
Send links to previous spreadsheet owners 27-OCT-19 12-APR-20 Open Pam King $1,000.00 $1,500.00
Customize solutions 19-OCT-19 11-JAN-20 Open John Watson $1,500.00 $4,000.00
Train developers / users 21-NOV-19 04-FEB-20 Pending John Watson $0.00 $8,000.00
Implement in Production 07-NOV-19 14-MAR-20 Open John Watson $200.00 $1,500.00
Migrate applications 26-OCT-19 01-JAN-20 Open Mark Nile $1,000.00 $8,000.00
Plan migration schedule 02-NOV-19 13-JAN-20 Open Mark Nile $1,500.00 $6,000.00
Publish Feedback application 06-NOV-19 15-MAR-20 Open Pam King $300.00 $12,000.00
Train developers on tracking bugs 01-DEC-19 20-JAN-20 On-Hold Myra Sutcliff $0.00 $2,000.00
End-user Training 08-NOV-19 03-JAN-20 Open John Watson $0.00 $2,000.00
Identify server requirements 12-SEP-19 13-SEP-19 Closed John Watson $100.00 $200.00
Specify security authentication scheme(s) 14-SEP-19 16-SEP-19 Closed John Watson $200.00 $300.00
Create pilot workspace 21-SEP-19 21-SEP-19 Closed John Watson $100.00 $100.00
Configure Workspace provisioning 21-SEP-19 21-SEP-19 Closed John Watson $200.00 $100.00
Run installation 22-SEP-19 22-SEP-19 Closed James Cassidy $100.00 $100.00
Obtain equipment specifications 14-NOV-19 17-NOV-19 Pending James Cassidy $0.00 $500.00
Purchase backup server 23-NOV-19 19-DEC-19 Pending Mark Nile $0.00 $3,000.00
Identify integration points 19-NOV-19 09-DEC-19 Pending Mark Nile $0.00 $2,000.00
Decommission machines 19-NOV-19 19-NOV-19 Pending Scott Spencer $0.00 $100.00
Map data usage 01-DEC-19 13-JAN-20 Pending Mark Nile $0.00 $8,000.00
Purchase new machines 05-JAN-20 30-JAN-20 Pending John Watson $0.00 $2,500.00
Import data 06-JAN-20 02-FEB-20 Pending John Watson $0.00 $1,000.00
Convert processes 14-DEC-19 11-FEB-20 Pending Pam King $0.00 $3,000.00